An air bend force chart or force chart breaks down a number of key components of sheet metal bending in an easy to reference format.
Bending force formula for sheet metal.
First let us calculate the v bending force.
Therefore even a simple bench with enough room to bend 3 m pieces will do the job.
Get to know them better to learn advance concept easily.
Where a is the bending angle t is the sheet thickness and r is the bending radius.
The tensile strength of ordinary materials σb 450n mm2 which can be substituted into formula 2 to obtain.
Where ossb is the outside setback.
My workpiece s bending line is 3 m so the overall needed force is 3 22 66 tonnes.
Die ratio 6.
Air bending one of the three types of bending for sheet metal where the outside mold line is not pressed against the die.
Bend length 3.
The bending force can be calculated from the sheet thickness die opening bend length and the ultimate tensile strength of the material.
Here end the fabrication formulas for sheet metal up next we ll be seeing some of the terminologies in sheet metal that you ll need.
R inner radius when the sheet is bent.
As explained in my first post the bend deduction can be calculated using the following equation.
The die ratio may be entered to calculate the die opening which is typically 6 to 18 times the sheet thickness.
Calculate the required force to bend a piece of sheet metal using v bending a process in which a v shaped punch presses the sheet into a v die.
Bend line shift bls the distance from the outside mold line to the original bend line on the flat pattern this is used to calculate the backstop location when working off of a flat pattern.
The gauge inside radius die opening and minimum flange length are all interconnected through different equations and relationships the air bend force.
The bending force calculation formula obtained here is very consistent with the data on foreign brochures.
Being able to read a bend force chart is crucial for any brake press operator and sheet metal engineer.
The lowest common bench capacity is around 100 tonnes.
Substitute the given values in the formula bf safetyfactor kfactor ultimatestrength bendlength thickness 2 dieopening.
Factor of safety 4.
Sheet thickness 3.
The required die width is 12 mm and tonnage per meter is 22.